Lifting engineering for the diaphragm wall reinforcement cages of a 39-storey tower at Broadbeach: cages up to 17.5 m long and about 13.6 t, picked flat, pitched and lifted upright.
The project
The basement of a 39-storey beachfront tower is retained by diaphragm walls, built panel by panel: a trench is dug under slurry and a reinforcement cage is lowered into it before the concrete goes in.
Each cage is up to 17.5 m long, 600 mm thick and about 13.6 tonnes, and it has to be lifted flat off the ground, pitched and turned upright without bending, twisting or letting a bar go. There were three kinds: straight panels, L-shaped corners and opener and closer panels.
What we did
Metric Engineering modelled the cages in 3D (Strand7) to find their weight and centre of gravity, and designed the lifting for each type: the pick points, the extra lifting bars, shear stoppers and Z-braces at those points, the welds, and a spreader beam so the vertical lift lines stay straight. Every lift case was checked with factors for dynamics and out-of-balance loads, to AS 3850, AS 3610 and AS 4100.
We issued lifting drawings for the horizontal, pitching and vertical lifts with a calculation report and certificate, and the cages were lifted to them.
Complete. The cages were lifted and placed to our design.