Inspection and pour approval of the wall formwork for a new beach reserve amenities building at Freshwater, with pour limits set to AS 3610.1.
The project
A new amenities building on the beach reserve at Freshwater, built in off-form concrete: cast-in-place walls with a regular grid of tie holes and a concrete roof slab.
The contractor built its own wall formwork from formply, timber walers and soldiers, and through-ties, and needed an engineer to check it and set safe limits before each pour.
What we did
Metric Engineering inspected the formwork before the first walls and again before the rest, and set the pour limits: 3.0 m lifts at no more than 1.0 m an hour, which keeps the concrete pressure to about 47 kPa (AS 3610.1) instead of 75 kPa if poured full height at once.
On the second inspection we recorded eleven items to fix, from walers that were not continuous to a tie without its bearing plate, then checked the fixes by photo and video call and approved the remaining walls to pour, on stated conditions.
The walls are poured and stripped: clean off-form concrete.