Black formply awning deck with curved yellow-edged forms over the Hall Street footpath, Bondi Beach

Projects/Bondi Beach

Hall Street, Bondi Beach

Role
Temporary works engineer for CEIG
Scope
Temporary Works · Class B Hoarding · Formwork Deck Design · Design Certificate
Year
2026
Location
Bondi Beach

A Class B hoarding over the Hall Street footpath that doubles as the formwork deck for the curved awning slab of a new mixed-use building, designed for CEIG.

The project

A new mixed-use building on Hall Street, Bondi Beach, one block from the beach. The Level 1 slab runs out over the footpath as an awning with a scalloped, curving edge, and the footpath below had to stay open to the public the whole time.

That meant one structure had to do two jobs: a Class B hoarding that keeps people walking safely underneath, and a deck strong and stiff enough to form and pour the awning slab on top of it.

What we did

Metric Engineering designed the hoarding as the falsework for the awning. Three lines of adjustable jacks carry LVL bearers and a ply deck, with a 1.2 m clear walkway kept open underneath and a deck-level walkway with edge protection out past the kerb.

We checked every stage of the pour, from the empty deck to the full slab, for the jacks, bearers, soles and deflection, and set the rules the crew builds to: concrete stops at the last jack line, bearers sit centred in the U-heads, and joints land over supports. The design was issued with a signed design certificate.

CEIG built it. The photos show their formwork: the curved edge forms follow the awning line cleanly, with tight joints and a flat, true deck.

The deck is formed and the reinforcement is in, with the footpath open below.

  • Temporary Works
  • Class B Hoarding
  • Formwork Deck Design
  • Design Certificate

How it works

One structure, two jobs.

A section through the hoarding. The footpath stays open under the deck while the awning slab is formed and poured on top of it.

  1. 1Awning slab, formed and poured on the deck
  2. 2Concrete stops at the last jack line
  3. 3Ply deck on LVL bearers
  4. 4Bearers centred in the U-heads, joints over supports
  5. 5Three lines of adjustable jacks on soles
  6. 61.2 m clear public walkway, ply hoarding both sides and over
  7. 7Deck-level walkway with edge protection past the kerb
A B C NEW BUILDING FOOTPATH ROAD KERB 1.2 m CLEAR 1 2 3 4 5 6 7
Section through the Class B hoarding, drawn for this page from our design.Not to scale

3D model

Walk around the hoarding.

Our temporary works model of the hoarding and awning deck, built from the issued design: jacks and frames, bearers, joists, the ply deck, the curved awning slab, the edge protection and the ply hoarding that encloses the public walkway on both sides and overhead. Drag to turn it, switch parts off to see under the deck, or cut down through it.

Show

Drag to turn. Open it full screen to zoom.Drag to turn. Scroll or pinch to zoom. Right-drag or two fingers to move.

Next projectWaterfront Home, East Hills

Send us your drawings.

We’ll reply within 24 hours with a fixed-fee proposal.

TransmittalTo: Metric Engineering

  1. 01Architectural plans
  2. 02Survey
  3. 03Geotechnical report
  4. 04Site photos

ReturnedFixed-fee proposal within 24 hours

Send what you have.