Temporary works at Sydney Airport's South-West Sector: formwork for new concrete valve pits, shoring boxes and road plates, and a certified support scheme for live pipework in an open pit.
The project
New reinforced concrete valve pits on the airport's fuel and pipeline network, built on an operating airfield where work windows are short and nothing can be left to chance.
The pits are tight: pipes, a sump and conduits pass through the walls, and the props across the pit had to fit around them.
What we did
Metric Engineering designed the vertical formwork for the pit walls (40 kPa, 1 m an hour, 300 mm layers, timber soldiers and walers with coil ties), through six revisions as the site changed, and the shoring boxes and steel road plates. When the props could not all fit on the short walls, we redesigned the layout on the day.
Later, after a pipe stand failed in another pit, we designed and certified three adjustable steel trestles to carry the remaining pipework, with hold points and a lifting sequence so the crane takes the load before any bolt is released.
Pit formwork built and poured; the support scheme certified and issued.