Falsework design for every suspended slab of a 31-level tower over four basements in North Sydney, and the propping for a 250 t mobile crane on the basement slabs.
The project
A post-tensioned residential tower of 31 levels over four basements in North Sydney, with a 1.4 m thick transfer slab at Level 1 and typical floors of 200 to 300 mm.
To build the tower crane, a 250 t-class mobile crane had to set up on the basement 1 loading bay, a slab that was never designed for it, with outrigger loads of about 820 kN each.
What we did
Metric Engineering designed the falsework for every slab, from the basements to Level 31: frame towers, bearers, joists and deck, with a leg spacing table by slab thickness so the crew can set out each pour, and a signed approval before each one.
For the crane, we designed propping that carries each outrigger down through basements 1, 2 and 3 to the slab on ground: 24 heavy-duty shore props in pairs, about 620 kN each, with the travel route and a pre-lift inspection.
In progress. The falsework is in use on site, level by level.