What OSD is
An OSD system stores runoff from roofs and paved areas in a tank or basin and releases it through a small outlet, usually an orifice plate, at a controlled rate. Councils set two numbers: how fast the site may discharge (the permissible site discharge) and how much it must store (the site storage requirement). The design has to show the system meets both for the storms council specifies, with a safe overflow when it fills.
When councils require it
There is no single Sydney rule. Each council sets its own triggers, usually by development type and by how much hard surface is added. Single dwellings are exempt in some areas and not in others. Some councils sit within catchments that use older catchment-wide handbooks. Others have rewritten their controls recently.
Sutherland Shire is a good example of why this matters. Its stormwater specification changed in late 2025: rainwater tanks no longer offset OSD for houses and dual occupancies, and charged drainage systems are not accepted except for basement car parks. A neighbour's approval from a few years ago is no guide to what will be approved now.
So always check three things: the current DCP and stormwater policy, your development consent conditions, and whether council's approval is needed for the connection to its drainage system. Complying development is not a way around it. The Housing Code does not set OSD itself, but where council's approval is needed to connect to its system, council applies its own controls to that approval.
Why feasibility comes first
The common late surprise is not the tank size. It is that the tank does not fit, or the water cannot get out. Before the plans are fixed, check:
- Lawful point of discharge. Where can the site legally drain to: the kerb, a council pipe, or an easement through a downstream lot? A site that falls away from the street may need an easement, and that can take months.
- Levels. The outlet has to sit above the kerb or pipe it drains to. On flat or low sites that controls how deep the tank can go.
- Space. Driveways, pools, trees, services, sewer mains and setbacks all compete for the same ground.
- Flood. On some sites the flood extent changes what is required, so check it early.
Fixing these at concept stage costs a sketch. Fixing them after the DA is approved can cost a modification.
What an OSD design package contains
- A stormwater plan showing roof and surface drainage, pits, pipes, the OSD system and the connection to the street or council system.
- OSD details: tank or basin dimensions, storage volume, outlet and orifice details, overflow and access for maintenance.
- Calculations, usually a hydraulic model, showing the permissible site discharge and storage are met, and pipe and pit sizing to AS/NZS 3500.3 and council's requirements.
- Structural design of the tank where it sits under a driveway or building.
- Any rainwater reuse tank required by BASIX, shown separately from the OSD storage where council requires that.
After construction
Most councils want a works-as-executed plan, prepared by a registered surveyor, showing what was built, and an engineer's certificate that it matches the design. Many also require a positive covenant and restriction on title so the system is kept and maintained. Plan for both before the occupation certificate.
Changing an existing OSD system
Owners often want to recover the yard an OSD basin takes up. A covenant usually means changes need council's consent, not that changes are impossible. The practical answer is normally to keep the same storage and discharge in a different form, such as converting a surface basin to an underground tank. We do not design decks or structures over an open basin: the basin has to stay open and maintainable.
See our civil and stormwater engineering service, the Vermont Street, Sutherland project, or send us the plans.