Crane on a suspended slab: back-propping design

A suspended slab is designed for the building it belongs to, not for a crane outrigger. When a crane, concrete pump or hoist has to set up on one, the slab needs checking and usually propping.

By Youssef Emad, BE Civil (Hons) · Updated 27 November 2026 · 6 min read · Illustrative image

When you need a temporary works engineer

Any time a heavy load sits on a suspended slab that was not designed for it. The common cases are:

  • a mobile crane setting up on a basement or podium slab, for example to erect or dismantle a tower crane;
  • a concrete pump, a materials hoist or a loading platform on a slab;
  • a new slab being poured while the slabs below are still young, which needs back-propping through several levels;
  • heavy plant, precast panels or steel bundles stacked on a slab.

If nobody can point to a calculation that shows the slab carries the load, it needs one. Raise it early: the lift date is usually fixed by the crane booking, and the props, mats and inspection have to be ready before then.

Why a slab needs propping

A crane outrigger concentrates a very large load onto a small pad. On our Walker Street, North Sydney project a 250 t-class mobile crane on a basement loading bay put about 820 kN onto each outrigger. A residential slab is designed for a fraction of that, spread over the whole floor.

The risks are punching shear around the pad, bending and cracking of the slab, and overloading the slab or columns below. Propping gives the load a path down through the levels to a slab on ground or to a level that has the capacity, so the slab under the crane only has to span between props.

What to send

  • Structural drawings for the slab and the levels below: thickness, reinforcement, post-tensioning if any, column and wall layout.
  • The crane: make and model, configuration, outrigger spread, and the maximum outrigger loads for the lift. These come from the crane supplier or the lift plan.
  • Outrigger pads or mats proposed, with sizes.
  • Concrete age and strength of each slab involved, and the date of the lift.
  • The prop system available on site, if you have a preference.
  • A marked-up plan of where the crane will set up and how it will travel in.

What the design covers

  • A check of the slab under each outrigger for punching, bending and shear, with the load spread through the mat.
  • A prop layout on each level below, with the prop type, capacity and load in each prop.
  • Checks of the lower slabs, including the slab on ground or footings that take the props.
  • The travel route, if the crane drives across the slab to its set-up position.
  • Conditions: minimum concrete strength, how props are installed and tightened, and when they can come out.
  • A design certificate, and a pre-lift inspection of the props.

Back-propping during construction

The same thinking applies to the normal pour cycle. When a new slab is poured, its weight and the formwork load go down through the floors below, which are still gaining strength. A back-propping design sets how many levels stay propped, at what spacing, and when each level can be stripped. On Lidcombe Central we issued the back-propping in staged packages across three towers over a transfer podium so the crews could cycle up the building without stopping.

On site before the lift

Before the crane sets up, the props are inspected against the drawing: positions, type, plumb, head and base plates, and that they are tight. Anything that does not match is fixed and checked again. The lift proceeds only once the inspection is signed off. After the lift, props come out in the order the design allows.

For crane, pump and hoist propping, see temporary works engineering or send us the details.

Need this designed or certified? Send your drawings and we will come back with a fixed-fee proposal within 24 hours.

Request a fee proposal

FAQs

Common questions

Who provides the outrigger loads?

The crane supplier or lift planner. The loads depend on the crane configuration, the counterweight, the radius and the load being lifted, so they come from the lift plan, not from a general figure.

Can the crane go on a post-tensioned slab?

Often, yes, but post-tensioned slabs need extra care. The tendon layout and any restrictions on drilling or point loads have to be in the design, so send the PT drawings.

How long does a back-propping design take?

Simple single-lift designs can usually be turned around in a few days once we have the drawings and crane loads. Multi-level back-propping for a pour cycle takes longer. Tell us the lift date at the start.

Send us your drawings.

We’ll reply within 24 hours with a fixed-fee proposal.

TransmittalTo: Metric Engineering

  1. 01Architectural plans
  2. 02Survey
  3. 03Geotechnical report
  4. 04Site photos

ReturnedFixed-fee proposal within 24 hours

Send what you have.