What AS 3610.1 covers
AS 3610.1 is the specification for formwork for concrete. It sets the loads formwork must be designed for, including the concrete, the people and equipment on the deck, stacked materials, the heaped load during placing and lateral loads, and the pressure of wet concrete on wall and column forms. It also sets out documentation and inspection, and the tolerances for the finished concrete.
Concrete pressure on vertical forms is a good example of why the design matters. On our Freshwater Reserve project we limited wall pours to 3.0 m lifts at no more than 1.0 m an hour, which kept the pressure to about 47 kPa instead of about 75 kPa if poured full height at once. The pour rate is a design condition, not a site preference.
What a formwork design includes
- Drawings of the deck system: sheeting, joists, bearers, props or frames, spacing, and bracing.
- A leg or prop spacing table by slab thickness, so the crew can set out each pour without a new design.
- Edge forms, set-downs, beams and any special areas such as transfer slabs or thick sections.
- For walls and columns: ties, walers, soldiers, the maximum pour rate and lift height.
- Stability: how the system resists lateral load and stays braced while it is built and struck.
- Back-propping of the slabs below, where the loads go into young concrete.
- General notes and conditions: materials, tolerances, eccentricity limits at prop heads, stacking limits and the stripping sequence.
Proprietary systems come with load tables, but the job-specific layout, the loads and the interface with the structure below still need designing.
Where formwork goes wrong
Most formwork problems we find at inspection are not in the design but in the gap between the design and the deck that was built:
- prop spacing stretched to suit the props on hand rather than the table;
- bearers sitting off centre in the U-heads, or joints landing between supports;
- props standing on fill, broken pavers or unsupported soles;
- bracing left out because it was in the way;
- a thicker slab section, a beam or a set-down poured on a layout designed for the typical slab;
- materials stacked on the deck before the pour beyond what the design allows.
Each of these changes the load path. A good design anticipates them with clear notes and simple tables, and the inspection catches the rest.
The formwork design certificate
The certificate is the engineer's signed statement that the formwork has been designed to AS 3610.1 and the other standards that apply, for a stated scope, on stated drawings. It should name the drawings and revision, the loads assumed, and the conditions the design relies on, such as pour rates, stacking limits, minimum concrete strength before stripping, and inspection hold points.
A certificate is only as good as the scope it names. If the pour sequence or slab thickness changes, the design and the certificate need revising.
Who signs it
The formwork designer signs the design certificate. In NSW that should be an engineer with the experience and qualifications for the work. Principal contractors, certifiers and SafeWork inspectors look for it, and many builders will not let a formwork contractor pour without it.
The pre-pour formwork inspection
Before concrete is placed, someone competent checks that what was built matches the design:
- prop or frame type, spacing and plumb, base plates and soles on firm ground or slab;
- bearers and joists: size, spacing, laps over supports, and bearers centred in the U-heads;
- bracing in place and connected;
- ties, walers and soldiers on wall forms, with bearing plates on every tie;
- edge protection and access;
- any conditions in the design, such as where the pour must stop.
Items that do not comply are listed, fixed and checked again before the pour is approved. See temporary works engineering or send us the formwork drawings.