Illustration of a Type B hoarding: a covered footpath walkway under a deck carrying site sheds, with a ply wall on the building side

Guides/Temporary works

Hoardings in the City of Sydney: Type A and Type B

The City of Sydney sees more hoardings than any other council in NSW: CBD towers, terraces and heritage buildings built hard to the footpath. Here is how its rules work and what the engineering has to cover.

By Youssef Emad, BE Civil (Hons) · Updated 27 November 2026 · 7 min read · Illustrative image

Why the City of Sydney is the one to plan around

Most buildings in the CBD, Pyrmont, Surry Hills, Redfern, Darlinghurst and Glebe sit right on the street boundary, with busy footpaths, street awnings and a lot of heritage fabric. Almost any work above ground on those sites puts the public at risk, so a hoarding is part of the job from day one, and the City's process sets the program.

The City publishes a Code of practice: construction-related temporary structures on and above roads, which sets the minimum standards, and approves hoardings under the Local Government Act 1993 and the Roads Act 1993. Other Sydney councils have their own policies, but the engineering is the same and the City's code is the most detailed, so it is a good benchmark wherever you are building.

Type A and Type B

  • Type A is a fence: generally a 2.1 m high ply sheet fence on a timber or steel frame along the site boundary. It keeps the public out but gives no protection from above.
  • Type B spans the footway (or part of the road) and gives the public overhead protection. People walk through a protected corridor under a deck while work goes on above.

Scaffolding on the street also needs a Type A fence at footpath level, and has to be set back from the kerb or protected with barriers, with an approved route for pedestrians. The code also covers cantilevered work platforms, perimeter screens, site sheds on decks and facade retention systems.

Which type you need comes down to the risk of something falling on the footpath: how close the work is to the boundary, how high it goes and how busy the street is. That is settled with the City in the application. The engineer's job is to make the chosen structure work.

Heritage buildings and creative graphics

The City requires creative graphics on construction hoardings: bespoke artwork approved by the City, one of its licensed artworks, or historic images. Where the hoarding surrounds a heritage-listed site, or sits in an area of heritage significance, it must display historic images of the locality. Plan the graphics into the application, because an image of the design is lodged with it.

Heritage sites also change the engineering. A hoarding beside a heritage facade should not rely on fixings into sandstone, render or original joinery, so the frame usually has to stand on its own, with bracing and counterweights instead of ties back to the wall. Existing street awnings, vault lights and cellars under old footpaths all need to be found before the frame is set out, so that loads go where the ground can take them.

What the engineer designs

For a Type B hoarding the design normally covers:

  • Loads. Wind on the panels and graphics (AS/NZS 1170.2), self weight, the rated deck load, and impact from objects falling onto the deck. The SafeWork NSW code sets out the requirements for overhead protection in public places near worksites.
  • The structure. Frame or jack spacing, bearers, the deck, bracing, and how it sits on the footpath without overloading pits, vaults or pavers.
  • Clearances. A clear walkway and headroom under the deck, clear of posts, pits, street furniture and existing awnings.
  • Edges and loading. Edge protection, toe boards, and how loads get onto and off the deck.
  • Kerb and traffic. Where the deck oversails the kerb, clearance to traffic and protection to the frame.

The deliverable is a hoarding drawing with general notes, the rated deck load stated clearly, and a design certificate, then an inspection once it is up. Cranes and hoists swinging over the road need their own approval: a hoarding approval does not cover them.

Site sheds, materials and formwork on the deck

A Type B deck is valuable space on a tight city site, and the City allows site sheds on decks where they meet the code. That only works if the deck is designed for them. A hoarding rated for light loads is not a materials platform, and it is not falsework.

On our Hall Street, Bondi Beach project the Type B hoarding was designed from the start as the formwork deck for a curved awning slab over the footpath. Jack lines carry LVL bearers and a ply deck, a clear walkway stays open underneath, and every stage of the pour was checked. The design set the rules the crew builds to, such as where the concrete stops and how bearers sit in the U-heads.

What to send for a hoarding design

  • The site plan and architectural plans showing the building line, footpath width, kerb and any street awning.
  • The City's requirements or permit conditions, and whether the site is heritage-listed or in a heritage area.
  • What the deck will carry: protection only, site sheds, materials or formwork.
  • The hoarding system you plan to use, if you have one.
  • Photos of the footpath: pits, vault lights, trees, poles and awnings.

With that we can return a fixed fee quickly. See our temporary works engineering service, or send us the drawings.

Need this designed or certified? Send your drawings and we will come back with a fixed-fee proposal within 24 hours.

Request a fee proposal

FAQs

Common questions

Do I need City of Sydney approval for a hoarding?

Yes. The City requires approval before any construction hoarding or scaffold goes up on a public road or footway, under the Local Government Act 1993 and the Roads Act 1993. Fees depend on the length, type and location, and on whether sheds sit on the deck.

Does a Type B hoarding need an engineer?

In practice, yes. A Type B spans over the public, so it needs a structural design, a certificate and an inspection once it is built. If the deck will carry sheds, materials or formwork, the design has to be done for that load.

What graphics go on a hoarding at a heritage site?

The City requires historic images of the locality on hoardings around heritage-listed sites or in areas of heritage significance. Elsewhere you can use City-approved bespoke artwork or one of the City's licensed artworks.

Can a Type B hoarding be used as formwork for an awning slab?

Yes, if it is designed as falsework for the full pour, with conditions on how it is built and where the concrete stops. A standard hoarding deck is not designed for wet concrete.

Send us your drawings.

We’ll reply within 24 hours with a fixed-fee proposal.

TransmittalTo: Metric Engineering

  1. 01Architectural plans
  2. 02Survey
  3. 03Geotechnical report
  4. 04Site photos

ReturnedFixed-fee proposal within 24 hours