Why boundary excavation needs a design
When a cut is close to a boundary there is no room to batter the ground back. The soil behind the cut, and anything sitting on it, has to be held up. The neighbour's footings, the footpath and the services in it all sit within the zone the excavation can affect. If the support moves too much, cracks appear next door. The design limits that movement, not just the risk of collapse.
Common shoring systems
- Piled walls. Contiguous or spaced bored piles, often with shotcrete between them, drilled before the excavation. In Sydney the piles are usually socketed into rock below the bulk excavation level.
- Cantilever piles. For shallow cuts, piles can stand as cantilevers. Deeper cuts need support near the top.
- Rakers. Inclined props from the wall down to footings or the base slab. They need room inside the excavation and get in the way of the permanent works, so the sequence matters.
- Ground anchors. Tensioned anchors drilled back behind the wall. They keep the excavation clear, but they extend under the neighbouring land, so check early whether the neighbours will consent.
- Propping by the permanent structure. Often the final answer: the basement slabs prop the wall, and the temporary supports come out in stages as each slab is poured.
The right system depends on depth, ground, the neighbours' structures, space on site and the construction sequence. On Gordon Street, Petersham and Cudgegong Road, Rouse Hill the shoring was designed together with the permanent structure and the sequence of the build.
What the design needs from the geotechnical report
Shoring design is only as good as the ground information. The geotechnical report should give:
- the soil and rock profile from boreholes, including depth to rock and rock class;
- design parameters for each layer: strength, unit weight, and earth pressure values;
- groundwater levels and whether dewatering is needed;
- allowable bearing and socket capacities for piles;
- advice on rock stability, defects and any need for rock bolting.
Collapsing several layers into one simplified profile can hide a weak layer. We design to the layers in the report.
Groundwater
Groundwater changes the design. Water pressure adds load to the wall, seepage through the face can carry soil with it, and dewatering can cause settlement of neighbouring ground. Sites near the harbour, rivers or beaches often have groundwater within the depth of a basement. The geotechnical report should say whether the wall needs to be close to watertight, whether dewatering is allowed, and whether a licence is needed. A shotcrete infill between piles that suits dry sandstone may not suit a wet sandy site.
Surcharges and the neighbours
The wall must carry more than the soil. It carries the neighbour's footings, the footpath and traffic, cranes and stockpiles near the edge. Each of these is a surcharge that the design includes. Where a neighbouring house sits close to the boundary, its footings may need underpinning or a stiffer wall to keep movement down.
Dilapidation and monitoring
Before excavation starts, a dilapidation survey records the condition of neighbouring buildings and the footpath, with photos of existing cracks. It protects everyone if there is a dispute later. During excavation, the wall and neighbouring structures are monitored, typically by survey targets read by a surveyor, against movement limits set in the design. The design states what happens if a trigger level is reached.
What to send
- Architectural and structural plans and sections of the basement.
- The geotechnical report.
- The site survey, showing neighbouring buildings and their distance to the boundary.
- Your proposed construction sequence and equipment, if known.