Why the inspection matters
Reinforcement does most of the work in a concrete element, and errors in it are invisible once the concrete is placed. A missing bar, a lap that is too short or reinforcement sitting on the formwork with no cover can all lead to cracking, deflection or long-term durability problems. A pre-pour inspection is the last chance to catch them.
Why the certifier asks for it
The certifier carries out the mandatory critical stage inspections, but certifiers are not structural engineers. For footings, slabs and other structural elements most certifiers ask for an inspection certificate from the engineer who designed the structure, confirming the work matches the approved drawings. Without it, the certifier may not accept the stage, and the final certificate can be held up.
What the engineer checks
- Bar size and spacing against the drawings, top and bottom, both ways.
- Laps and anchorage: lap lengths, cogs and hooks where shown.
- Cover: bar chairs and spacers at the right height and spacing, so the steel sits where it was designed.
- Extra bars at openings, re-entrant corners, set-downs and around penetrations.
- Starter bars for walls and columns in the right place.
- Footings: founding material as described in the design or the geotechnical report, and clean excavations.
- Penetrations and cast-in items that affect the structure.
- For post-tensioned slabs, the tendon layout and anchorages, where we designed them.
The inspection is visual and measured with a tape. We do not take levels or survey readings on site. Set-out and levels are checked by the builder or a surveyor.
Defects we see most often
- Bar chairs missing or crushed, so bottom bars sit on the formwork with little or no cover.
- Top reinforcement walked flat by trades before the pour.
- Trimmer bars left out around penetrations and set-downs added late.
- Laps placed at the point of highest stress, or shorter than the drawings show.
- Starter bars in the wrong position for walls or columns that were moved on a later revision.
- Edge beams and thickenings dug to the wrong depth, or footings not taken to the founding material described in the design.
- Work built to a superseded drawing revision.
Most of these take minutes to fix before the pour and are very expensive to fix after it.
What happens after
If everything complies, the pour is approved and the inspection certificate follows. If not, the items are listed with photos, the builder fixes them, and they are checked again, by a return visit or by photos where the item allows. On the waterfront home at East Hills we inspected the reinforcement at each stage, from the foundations to the roof slab, over six visits. On a new home in Strathfield we inspected each stage and issued the final structural certificate when the house was finished.
How to book so the pour is not held up
- Book a day or two ahead, and confirm the day before.
- Have the reinforcement complete, chaired and tied, not still being placed.
- Keep the current approved structural drawings on site.
- Clear the area of loose material and standing water.
- Have someone on site who can fix minor items on the spot.